...
Tasklist |
---|
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|T|M|F|1334160996090|1334161004643|pmccullough|notify DBI "replication down"|
|F|M|F|1332430770793| |jjohnson|Obtain, confirm local DB backup|
|T|M|F|1330129954503|1334161333868|pmccullough|stop DB replication to SD PROD DB|
|T|M|F|1332435147646|1334161696862|pmccullough|web$ sudo /etc/init.d/httpd stop|
|T|M|F|1332435371673|1334161698378|pmccullough|geo$ sudo dtomcat5 stop -force|
|T|M|F|1332435313780|1334161702944|pmccullough|db$ sudo -u postgres /usr/pgsql-9.0/bin/pg_ctl -D /data/9.0/data -m fast stop|
|F|M|F|1330129954504| |pmccullough|halt linux on SD servers ($ sudo shutdown -h now)|
|F|M|F|1332954968696| |jjohnson|Carinet will provision the new IPs on the new sub-net|
|F|M|F|1332435543944| |jjohnson|/usr/pgsql-9.0/bin/pg_ctl -D /data/9.0/data -m stop on db server|
|F|M|F|1332435695769| |jjohnson|sbin/shutdown -h now on db server|
|F|M|F|1332954987678| |jjohnson|SF will give the go-ahead to Carinet to proceed|
|F|M|F|1330129954505| |jjohnson|CARI.net will ensure STD-ESXI/E3_1230-04-QCE server is shutdown and will transport hardware to proper chassis in order to fit the rack in C2 datacenter.|
|F|M|F|1332367258473| |jjohnson|Once in C2 datacenter, CARI.net will re-ip server from 209.126.178.66 to NAT 10.224.211.12/66.240.211.12|
|F|M|F|1332955152821| |jjohnson|Using the new IP, SF will connect to the STD-ESXI/E3_1230-04-QCE server as the ESXI host via the VSphere Client|
|F|M|F|1332955487194| |jjohnson|Once connected, SF will power on the VMs in sequence: VCenter VM VCenter17870, Prod-DB, Prod-Geo, and Prod-Web|
|F|M|F|1332955251938| |jjohnson|SF will then assign the new assigned IPs on the 10.224.211.x subnet to each of the 4 VMs, and make additional necessary configuration changes within the the VMs.|
|F|M|F|1330130511606| |jjohnson|SF will then test VPN connectivity to the VMs using SSH Putty sessions.|
|F|M|F|1330130294130| |jjohnson|confirm services db, geo, web|
|F|M|F|1330131612467| |jjohnson|test SD application (read only)|
|F|M|F|1332430506986| |jjohnson|resynch db replication|
|F|M|F|1332430580587| |jjohnson|test SF application (confirm replication)|
|F|M|F|1332430597708| |jjohnson|SD PROD WEB into standby|
|F|M|F|1332955338085| |jjohnson|If connectivity is successful, then we are done; if not, then SF and Carinet will work together to ensure the VPN tunnel is working correctly on the new shared firewall.|
|F|M|F|1330130341395| |pmccullough|decommission existing carinet firewall (carinet)|
|F|M|F|1332955592194| |jjohnson|decommission additional storage server STD-CUSTOM/NEHALEM_EN_3440-04-QCE (sfgovstor01.aspadmin.net-209.126.178.126)|
|F|M|F|1334157639016| |jjohnson|Decommission Private V-LAN|
|