Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Table of Contents
1.0 Release

We are now in our production env (hosted VMWare at carinet).
DEV http://209.126.178.81/
QA http://209.126.178.71/
PROD http://209.126.178.76/
All ETLs are running including AVS ReloadCOIT and .

AVS Reload

Review report (see attached) and examine results.
We need DBI to steer improvements.
I think we can increase the retirement successes without much more cost.
Can we get create and retire dates in the export file?

Announce 1.0 Release

Production Readiness - Ongoing

1.1 We need to announce a 1.0 Release for the budget cycle.
Would DBI be willing to join us in a COIT meeting to announce this release?

Production Readiness
  • Ongoing during 1.0
  • Complete before 1.1
1.1 Release
  • AVS Integration fully tested
  • EAS prodcution readiness complete