Preamble
This page serves as a plan for parallel testing EAS and AVS.
During this exercise, we will use DBI QA (concrete name is DEV3) and EAS PROD.
We can use EAS PROD because it is not in PROD.
EAS will be in PROD after this release.
...
DBI reserves the right to run in parallel for longer than 3 weeks if necessary.
During this testing, EAS support shall available during business hours.
- Paul 415-889-3963
- Jeff 415-722-0061
Refresh AVS QA from AVS PROD Prepare Databases (Nov 1) (DONE)
...
- confirm that the Change Notification is configured with DBI QA as target.
- For every address modified in AVS PROD, make the same changes in EAS PROD.
- At the end of each day, confirm that AVS QA and AVS PROD are materially the same.
- TODO - does AVS have a way to extract "changes since yesterday"?
Notes
- DBI reserves the right to run in parallel for longer if
- EAS support shall available during business hours