This is the tentative schedule for the 1.1 release.
The issue list for the 1.1 release is here http://code.google.com/p/eas/issues/list?can=2&q=Milestone%3DRelease1.1
Based on our rate of progress over the last few weeks of work on production
readiness, it seems to me that it is reasonable to pick a release date of Sept 19.
Given that release date I'd like to propose the plan as follows.
Aug 29 - Sept 2
Integration Testing
Complete Monitoring Setup
Sept 6 - Sept 9
Parallel testing
Spet 12 - Sept 16
Parallel testing
Sept 19 - Sept 23
Failover testing
Sept 26
go live